Hines Development For Bergamot Area Slogs Through Planning

Posted Sep. 20, 2013, 8:28 am

Parimal M. Rohit / Staff Writer

A development agreement (DA) proposing to bring 471 rental housing units and as much as 375,000 square feet of creative office space to Bergamot Station and the Transit Village Center at 1681 26 Street has been deliberated by Santa Monica’s planning commissioners for the past two weeks.

The consideration of the potential DA, proposed by Hines/26th Street LLC (Hines), at the Planning Commission at their Sept. 11 and 18 meetings coincided with the City Council green lighting the Bergamot Area Plan Sept. 10.

Hines presented its plans to commissioners Sept. 11, proposing a development “setting the standard for a sustainable future” and would feature a combination of five residential and creative office buildings, four acres of open space, two acres of parks, paseos, and plazas, two acres of streets and sidewalks, and a 31,675-square foot public plaza.

According to the Hines Power Point presentation, there would be 498 total residential units spread across three buildings, with 471 of those units available for rent. The other 27 units would be reserved for 27 artist live/work spaces.

Hines estimates about 40 percent of the units would be either two or three bedrooms, which City Hall believes will bring in more families and limit the number of transient occupants.

As many as 90 units would be ground level and have a direct entry.

Two creative office buildings are also proposed. In addition to nearly 375,000 square feet dedicated to creative office space, another 29,000-plus square feet are proposed for restaurant and retail space.

Also proposed by Hines is a three-level subterranean parking garage with 1,936 parking spaces, 1,300 bicycle parking spaces, 340 lockers, and 22 showers.

The proposed project’s floor-area ratio, or FAR, is currently at 2.47, according to the Hines Power Point presentation.

Hines also proposed “the most aggressive TDM plan ever implemented.” TDM is short for Transportation Demand Management.

The proposed TDM plan calls for stiff penalties for failure to meet caps imposed upon vehicle trips.

Under the current proposal, Hines predicts the project, once complete, would generate 519 vehicle trips during peak pm hours. The Land Use and Circulation Element (LUCE) requires Tier 3 projects such as this one to produce no more than 843 vehicle trips during peak pm hours.

Some incentives offered to those who would live or work at the proposed Hines project include: residential transit pass subsidy; commercial parking cash payout; van pool subsidies; bike share contribution; reserved spaces for carpoolers and car shares; and, pedestrian wayfinding, among others.

In terms of community benefits, Hines’ representatives state the proposed project would offer new affordable and workforce housing, reduce greenhouse gas emissions and congestion, provide infrastructure and open space improvements, incorporate social and cultural facilities, and maintain historic preservation.

Financially, the Hines project, if realized in its current iteration, may result in $106 million in community benefits over the course of 55 years, including annual contributions of $200,000 for childcare, $25,000 for bike share, $15,000 for transportation management, and $5,000 for historic preservation.

The proposed project would also include 50 deed-restricted housing units and ongoing local hiring, local preference housing, and artist preference programs.

The Hines team also proposed a few one-time community benefits, such as constructing streets, sidewalks, and signals, contributing $2 million for the Expo Buffer, and directing $160,000 to the Big Blue Bus. Another $75,000 would be doled out for historic preservation.

During construction, the Hines team assured they would institute a local hiring program. The development proposes to be LEED Gold Certified.

Other potential benefits include 25 “extremely low-income” housing units, 2,109 permanent jobs, $385 million in annual economic output, $2.5 million payment for on-site public art, and a $5.1 million transportation impact fee payment, among others.

In all, the Hines team estimates the proposed project would have a net fiscal impact of $25 million to the City’s General Fund over the life of the project.

The Hines team did acknowledge in its presentation a few remaining “open items,” such as the “affordability level” of the 50 affordable housing units, how the proposed parking cash out program would be applied to parking not subsidized by employers, how flexible sustainability standards would be in order to allow for technology advances, and the “construction of additional affordable units on-site in lieu of payment of a commercial affordable housing linkage fee.”

In addition to outlining all the relevant statistics of the proposed DA, the Hines presentation also included several renderings of how the development would look like if it were built.

Beyond the project’s plans, planning commissioners were also presented with the Final Environmental Impact Report (FEIR).

City staff’s presentation and the response of commissioners to Hines’ DA request will be covered in next week’s issue of The Mirror.

Post a comment

Comments

Sep. 21, 2013, 12:04:18 am

Caron Block said...

As it is, the citizens of Santa Monica cannot drive east after 3 pm without getting stuck in horrendous traffic until you get east of the 405. Now it is getting more difficult to go south on major streets like 26th St. It is getting to the point that we are. " locked" in Santa Monica. Perhaps that is the goal of the Santa Monica City Council in order to make sure no money is ever spent outside the city limits. But the overdevelopment both commercial and residential is destroying our quality of life, affecting out reputation, and hurting tourism ( some people are afraid once they come to Santa Monica they won't be able to leave.) We are no longer a laid back beach city. We are just a smaller version of everything that is wrong with Los Angeles.

Jan. 29, 2014, 4:04:46 pm

GAP Santa Monica said...

What about the TDM in five or ten years? After the location is built what if the traffic is far in excess of even the largest TDM number? Is the penalty going to take care of all the negative results? I don't think so do you? $106 million. How desperate do you think Santa Monicans are? Take your $2 million a year for 55 years and shove it.

SM Mirror TV