June 1, 2025 Breaking News, Latest News, and Videos

Two-Year Permit Approval Nightmare Finally Ends For Santa Monica Resident:

For more than two years, Santa Monica resident and home developer John Youngman has been battling the city for approval of his water recycling system at 303 22nd Street.

Last Friday afternoon, the nightmare finally came to an end, but Youngman says the delay caused by the City’s permit approval system and internal city staff rivalry has cost him at least $50,000 and put the project several months behind schedule.

The saga started in 2009, when Steve Bilson of ReWater Systems filed the original permit on behalf of Youngman. Bilson was hired as the contractor because he had successfully obtained a permit for an identical ReWater system at 222 Palisades Avenue without any hassles just weeks prior.

The permit was for two environmentally friendly “green” water systems. The first was a grey water system that captures, filters, and reuses water from the shower, tub, bathroom sink, and laundry for an underground drip irrigation system in the yard. The second was a storm water system that collects rain from the roof and is stored in a 5000 gallon underground tank, which is also used in the yard if the grey water system runs out of water when the irrigation system kicks-in at midnight.

Since City staff had previously issued an identical permit to Bilson in just two months, Youngman hoped he would have the same success, but it could not be any further from the case.

“The only part of the state code that had changed since then that was relevant to this system versus the previous system was that the grey water emitters can now be two inches deep versus the previous nine inches,” Bilson said. “Because the code was essentially the same, and the system was identical, permitting this system was easier for the city’s plumbing plan checker, Shane Peters, but it was not easier for their public works plan checker, Kit Dallarte.”

The original permit lodged in early 2009 was a paper application, which was the city’s former way of doing business. However, amongst all the delays, the City’s ePlan system came into action on Nov. 1 last year, where all permit submissions had to be submitted electronically.

“Kit (Dallarte) approved the complete ReWater system from Public Work’s perspective back then almost two years ago.” Bilson said. “What screwed everything up was an internal rivalry between Kit and the more citizen-friendly Shane (Peters) in Building and Safety. Kit would not accept Shane approving anything that Kit unilaterally decided was under Public Work’s jurisdiction, despite the meeting of virtually everyone in the city involved with this permit whereby everything for the permit had been ironed out.”

Bilson said Shane Peters eventually asked him to split up the ReWater system application into two parts and draw the system as two separate systems. One drawing would fall exclusively under the plumbing code, and would consist of what is traditionally considered plumbing stuff (pipes inside the house), and the other drawing would include everything else that Kit Dallarte considered under his purview, which was everything outside the house including the irrigation system, Bilson said.

Bilson said this was bizarre for a couple of reasons.

“First, the entire grey water irrigation system code including everything outside the house is found in the state plumbing code; there is really no good reason for Public Works to be involved in this type of permitting to begin with,” he said. “Second, splitting the system into two drawings was a facade, as the ‘plumbing’ aspects of the system are inseparable from the ‘other’ aspects of the system. I don’t know how you show a functional system if a pipe connecting the grey water filter to the underground drip irrigation system can’t connect on the drawing?”

With the ReWater system artificially “split up,” neither system depicted could actually work in the real world, but those two drawings were what it took to satisfy Kit Dallarte, according to Bilson.

“The one and only problem with that facade was that Kit then found the drawings to be incomplete,” Bilson said. “Whether later he spaced out and forgot that he’d demanded those two drawings, or later determined that he didn’t want to admit he’d demanded those two drawings, he eventually wrote notes to the effect that the drawings stunk and put those notes on the city’s ePlan program.”

The next problem was that neither Bilson nor Youngman were ever told Kit Dallarte’s notes had been entered on the ePlan program.

“We weren’t looking for them there when we were trying to locate them to determine the problem, and didn’t know to ask people to look there until recently,” Bilson said. “Another problem was that ePlan does not notify one city staffer when another city staffer makes notes that halt a permit process, and Shane did not realize what Kit had said or done in his new notes, because Kit wasn’t talking with him anymore. Perhaps the biggest problem was that Kit would not return anyone else’s phone calls either, until very recently.”

Youngman said he was frustrated with delays, saying it had slowed him down “two to three months” and when converted to a cash value, “at a raw cost, we’re probably talking $50,000.”

“(City staff) don’t seem well versed with their own system, they don’t understand it that well, I don’t know if they’ve been properly trained, but it seems to be very confusing for them,” Youngman said. “The real issue that I see, is that there is very little incentive on their part to learn it, to help you out, to speed things up, it’s kind of like ‘it doesn’t work that well, it’s just going to take longer’.”

He said what made matters worse was the fact there was no recourse for city employees if they held up projects.

“These people are very independent, very powerful,” he said. “I have no idea how they get hired and fired, I don’t think they ever get fired, but it’s just so frustrating because months go by. It’s zero downside on their part for inaction, and it costs me a fortune when they don’t follow through and do what they say they are going to do.”

Last Thursday, Bilson said he met with Mark Cunoe, Kit Dallarte’s new boss, and explained to him the entire situation. On Friday at about 4:30 p.m., Cuneo called to say the permit had finally been issued.

Ron Takiguchi, a City of Santa Monica building official, said two years far exceeded the expectations that the City wanted to permit something.

“Since grey water was somewhat new, the requirements were not fully known by the applicant, on both sides,” Takiguchi said. “I’m not pointing fingers here. This is a system that was custom, and an item that had to be detailed very much. It wasn’t a simple grey water system.”

He said the ePlan system still had improvements to be implemented to speed up the permit approval process.

He said he was currently in discussion with the software vendor to explore the option of a parallel review, meaning that each separate entity within the city such as the Fire Department, Building Safety, Public Works, Transportation, Planning, could process applications quicker than the current “serial review” system.

The “serial review” system does not allow one department to upload its new notes/plans until all other departments are all at the same stage.

“A plan has to go to several different city departments, so the applicant would have to wait until all departments are finished before they could upload the next version,” Takiguchi said.

The ePlan system currently does not cater to Macintosh/Apple users, as it only accepts Internet Explorer, another problem Takiguchi is working with the vendor to fix.

While this particular nightmare may be over, Bilson is concerned that Dallarte is still working for the city as he may have “an axe to grind,” and Bilson worries this particular type of nightmare can happen again to anyone who tries to obtain a permit.

Keep Up-To-Date With The Mirror:

Follow The Mirror on Twitter: twitter.com/SMMirror

Follow The Mirror on Facebook: facebook.com/SMMirror

in News
<>Related Posts

Defensible Space, Defined: How A Plus Tree Protects Communities from Wildfire

May 30, 2025

May 30, 2025

In the wildfire-prone landscapes of the Western United States, safeguarding homes and communities requires proactive measures. A Plus Tree, a...

Westside Ballet to Present Spring Showcase and Gala Featuring NYCB Stars This Weekend

May 30, 2025

May 30, 2025

The Huntley Santa Monica Beach Community Service Award will go to first responders from Los Angeles and Santa Monica in...

Salt & Straw Unveils Summer Pie Series with Five Seasonal Ice Cream Flavors

May 30, 2025

May 30, 2025

Five New Flavors Inspired by Classic Summer Pies Will Be Introduced Salt & Straw is giving summer a scoopable twist with...

Palisades Village to Reopen in 2026 with Revamped Retail, Dining, and Community Spaces

May 29, 2025

May 29, 2025

Elysewalker Set to Return With Park Reconstruction, Holiday Events, and Streetscape Upgrades Palisades Village, the open-air shopping and lifestyle destination...

(Video) Signs That Your Aging Loved Ones Are in Need of Caregiving

May 29, 2025

May 29, 2025

To Find Out More, Go To Safelyhomeagain.com To Find Out More, Go To https://t.co/ZcOduvaP03 pic.twitter.com/9E2uPzzZO6 — Santa Monica Mirror (@SMMirror)...

(Video) Last Thursday Concert Series Kicks off at Venice Boardwalk

May 29, 2025

May 29, 2025

The shows happen at Dudley Ave. at the pergolas on the north end of the boardwalk The shows happen at...

Santa Monica Public Library Launches Summer Reading Program to Promote Literacy

May 29, 2025

May 29, 2025

Running from June 14 through August 16, the program encourages participants of all ages to track their reading progress and...

Film Review: Jane Austen Wrecked My Life

May 29, 2025

May 29, 2025

FILM REVIEWJANE AUSTEN WRECKED MY LIFERated R98 MinutesReleased May 30th Jane Austen Wrecked My Life is a refreshingly simple and...

Burger Chain Tied to Late Rapper Nipsey Hussle Announces Venice Boardwalk Location

May 29, 2025

May 29, 2025

The announcement marks the brand’s expansion from its Fairfax District debut earlier this year Marathon Burger, a new franchise honoring...

Levain Bakery Debuts ‘Levain à la Mode’ with Local Ice Cream Partners for Summer

May 29, 2025

May 29, 2025

Seasonal Offering With Wanderlust Creamery is a First in Cookie Shop’s History For the first time in its three-decade history, Levain...

Bay Cities Italian Deli Responds to Health Code Closure, Commits to Corrective Action

May 29, 2025

May 29, 2025

Santa Monica Landmark Disputes Rodent Claims but Acknowledges Violations Bay Cities Italian Deli, a Santa Monica staple renowned for its...

(Video) Interviews with Rick Caruso and Elyse Walker, with a Dennis Quaid cameo

May 28, 2025

May 28, 2025

We spoke at the Press Conference to announce plans to reopen Palisades Village Shopping Mall. Actor Dennis Quaid arrives to...

Santa Monica Landlord to Pay $685K in Tenant Harassment Lawsuit

May 28, 2025

May 28, 2025

The settlement, announced Tuesday, resolves allegations of tenant harassment and discrimination under the city’s Tenant Harassment and Housing Anti-Discrimination ordinances...

Film Review: Bring Her Back

May 28, 2025

May 28, 2025

By Dolores Quintana Grief is the price of love.  Danny Philippou and Michael Philippou’s second feature film, Bring Her Back,...

County Assessor Stresses Need For Fire-Affected Households to Update Addresses to Receive Relief Checks

May 28, 2025

May 28, 2025

Assessor’s Office Offers Automatic Tax Relief for Fire-Affected Homeowners Following the destruction caused by wildfires earlier this year, the Los...