May 5, 2024 Breaking News, Latest News, and Videos

Two-Year Permit Approval Nightmare Finally Ends For Santa Monica Resident:

For more than two years, Santa Monica resident and home developer John Youngman has been battling the city for approval of his water recycling system at 303 22nd Street.

Last Friday afternoon, the nightmare finally came to an end, but Youngman says the delay caused by the City’s permit approval system and internal city staff rivalry has cost him at least $50,000 and put the project several months behind schedule.

The saga started in 2009, when Steve Bilson of ReWater Systems filed the original permit on behalf of Youngman. Bilson was hired as the contractor because he had successfully obtained a permit for an identical ReWater system at 222 Palisades Avenue without any hassles just weeks prior.

The permit was for two environmentally friendly “green” water systems. The first was a grey water system that captures, filters, and reuses water from the shower, tub, bathroom sink, and laundry for an underground drip irrigation system in the yard. The second was a storm water system that collects rain from the roof and is stored in a 5000 gallon underground tank, which is also used in the yard if the grey water system runs out of water when the irrigation system kicks-in at midnight.

Since City staff had previously issued an identical permit to Bilson in just two months, Youngman hoped he would have the same success, but it could not be any further from the case.

“The only part of the state code that had changed since then that was relevant to this system versus the previous system was that the grey water emitters can now be two inches deep versus the previous nine inches,” Bilson said. “Because the code was essentially the same, and the system was identical, permitting this system was easier for the city’s plumbing plan checker, Shane Peters, but it was not easier for their public works plan checker, Kit Dallarte.”

The original permit lodged in early 2009 was a paper application, which was the city’s former way of doing business. However, amongst all the delays, the City’s ePlan system came into action on Nov. 1 last year, where all permit submissions had to be submitted electronically.

“Kit (Dallarte) approved the complete ReWater system from Public Work’s perspective back then almost two years ago.” Bilson said. “What screwed everything up was an internal rivalry between Kit and the more citizen-friendly Shane (Peters) in Building and Safety. Kit would not accept Shane approving anything that Kit unilaterally decided was under Public Work’s jurisdiction, despite the meeting of virtually everyone in the city involved with this permit whereby everything for the permit had been ironed out.”

Bilson said Shane Peters eventually asked him to split up the ReWater system application into two parts and draw the system as two separate systems. One drawing would fall exclusively under the plumbing code, and would consist of what is traditionally considered plumbing stuff (pipes inside the house), and the other drawing would include everything else that Kit Dallarte considered under his purview, which was everything outside the house including the irrigation system, Bilson said.

Bilson said this was bizarre for a couple of reasons.

“First, the entire grey water irrigation system code including everything outside the house is found in the state plumbing code; there is really no good reason for Public Works to be involved in this type of permitting to begin with,” he said. “Second, splitting the system into two drawings was a facade, as the ‘plumbing’ aspects of the system are inseparable from the ‘other’ aspects of the system. I don’t know how you show a functional system if a pipe connecting the grey water filter to the underground drip irrigation system can’t connect on the drawing?”

With the ReWater system artificially “split up,” neither system depicted could actually work in the real world, but those two drawings were what it took to satisfy Kit Dallarte, according to Bilson.

“The one and only problem with that facade was that Kit then found the drawings to be incomplete,” Bilson said. “Whether later he spaced out and forgot that he’d demanded those two drawings, or later determined that he didn’t want to admit he’d demanded those two drawings, he eventually wrote notes to the effect that the drawings stunk and put those notes on the city’s ePlan program.”

The next problem was that neither Bilson nor Youngman were ever told Kit Dallarte’s notes had been entered on the ePlan program.

“We weren’t looking for them there when we were trying to locate them to determine the problem, and didn’t know to ask people to look there until recently,” Bilson said. “Another problem was that ePlan does not notify one city staffer when another city staffer makes notes that halt a permit process, and Shane did not realize what Kit had said or done in his new notes, because Kit wasn’t talking with him anymore. Perhaps the biggest problem was that Kit would not return anyone else’s phone calls either, until very recently.”

Youngman said he was frustrated with delays, saying it had slowed him down “two to three months” and when converted to a cash value, “at a raw cost, we’re probably talking $50,000.”

“(City staff) don’t seem well versed with their own system, they don’t understand it that well, I don’t know if they’ve been properly trained, but it seems to be very confusing for them,” Youngman said. “The real issue that I see, is that there is very little incentive on their part to learn it, to help you out, to speed things up, it’s kind of like ‘it doesn’t work that well, it’s just going to take longer’.”

He said what made matters worse was the fact there was no recourse for city employees if they held up projects.

“These people are very independent, very powerful,” he said. “I have no idea how they get hired and fired, I don’t think they ever get fired, but it’s just so frustrating because months go by. It’s zero downside on their part for inaction, and it costs me a fortune when they don’t follow through and do what they say they are going to do.”

Last Thursday, Bilson said he met with Mark Cunoe, Kit Dallarte’s new boss, and explained to him the entire situation. On Friday at about 4:30 p.m., Cuneo called to say the permit had finally been issued.

Ron Takiguchi, a City of Santa Monica building official, said two years far exceeded the expectations that the City wanted to permit something.

“Since grey water was somewhat new, the requirements were not fully known by the applicant, on both sides,” Takiguchi said. “I’m not pointing fingers here. This is a system that was custom, and an item that had to be detailed very much. It wasn’t a simple grey water system.”

He said the ePlan system still had improvements to be implemented to speed up the permit approval process.

He said he was currently in discussion with the software vendor to explore the option of a parallel review, meaning that each separate entity within the city such as the Fire Department, Building Safety, Public Works, Transportation, Planning, could process applications quicker than the current “serial review” system.

The “serial review” system does not allow one department to upload its new notes/plans until all other departments are all at the same stage.

“A plan has to go to several different city departments, so the applicant would have to wait until all departments are finished before they could upload the next version,” Takiguchi said.

The ePlan system currently does not cater to Macintosh/Apple users, as it only accepts Internet Explorer, another problem Takiguchi is working with the vendor to fix.

While this particular nightmare may be over, Bilson is concerned that Dallarte is still working for the city as he may have “an axe to grind,” and Bilson worries this particular type of nightmare can happen again to anyone who tries to obtain a permit.

Keep Up-To-Date With The Mirror:

Follow The Mirror on Twitter: twitter.com/SMMirror

Follow The Mirror on Facebook: facebook.com/SMMirror

in News
Related Posts

Wise & Healthy Aging Goes Gray on Denim Day

May 3, 2024

May 3, 2024

In observance of April’s Sexual Assault Awareness Month, a nonprofit that advances the dignity and quality of life for older...

Beck to Perform at Venice Family Clinic’s Inaugural HEART Gala

May 3, 2024

May 3, 2024

Among the expected talent attendees are Anjelica Huston, Chuck Lorre, Elisabeth Shue, Richard Chamberlain, Robby Krieger, Tom Morello Venice Family...

Santa Monica Mayor Joins Karen Bass in Urgent Talks on Homelessness Crisis

May 3, 2024

May 3, 2024

City Leaders Lobby Federal Lawmakers for Solutions During Washington DC Visit Santa Monica Mayor Phil Brock joined Los Angeles Mayor...

UCLA Faculty Group Demands Amnesty for Palestine Protesters, Issues Statement of Support

May 3, 2024

May 3, 2024

Faculty Calls for Legal Protection After Violent Crackdown on Campus Demonstration A group of UCLA faculty members have issued a...

(Video) New Interactive Kiosk Gives Downtown Passerby Details on Local Attractions, Public Transit

May 3, 2024

May 3, 2024

The Kiosk Will Reportedly Give the City of Santa Monica 50% of Revenue @smmirrornews The Kiosks are a new fun...

Police Seek Suspect Who Burglarized Downtown Santa Monica Office Building

May 2, 2024

May 2, 2024

The Building Houses the Offices of a Legal Services Company and a Local Newspaper By Zach Armstrong An investigation is...

Human Rights Play Center Stage with Two Award-Winning Films Opening this Weekend at Laemmle Monica Film Center

May 2, 2024

May 2, 2024

Cinema Libre Studio, a Burbank-based independent distribution company with a focus on social issue films, has two powerful films opening...

UCLA Gaza Solidarity Encampment Dismantled After Night of Counter Protesters’ Violence

May 2, 2024

May 2, 2024

LAPD and Other Agencies Sent in For “Student Safety”, Students Arrested  The UCLA Gaza Solidarity Encampment was removed during the...

UCLA Gaza Solidarity Encampment Attacked by Counter-Protesters During the Night/Early Morning Hours

May 2, 2024

May 2, 2024

Violence Erupts as Demonstrators Face Aggression During Tense Overnight Attacks On the night and early morning of April 30 into...

(Video) Footage of the Violent Counter Protesters at UCLA. TW: For Language and Violence

May 2, 2024

May 2, 2024

This reporter was grabbed and cursed at the end of the video. @smmirrornews Footage of the Violent Counter Protesters at...

Reactions From Local Authorities About the Violent Attacks April 30 at UCLA

May 2, 2024

May 2, 2024

Condemnation for the Incident and How it Was Handled Pour In After the terrifying events on the night and early...

Cinco de Mayo Festival Coming to Oakwood Park This Weekend

May 1, 2024

May 1, 2024

Revelers Can Expect to Be Entertained by Aztec Dancers, Grupo la Rosa Folklorico Dancers, and Charro (Mexican Dancing Horses) The...

These Bike-Centric Events Are Coming to Santa Monica This Month

May 1, 2024

May 1, 2024

The Festivities Extend Beyond May, With the Aids/Lifecycle Finish Line Festival on June 8 As Bike Month kicks off, the...

Hotel Labor Disputes End in Santa Monica

May 1, 2024

May 1, 2024

Key Highlights of the Agreement Include $5 per Hour Raise in the First Year, and Wage Increases of up to...

“Days Like These” Art Exhibition Coming to Bruce Lurie Gallery

May 1, 2024

May 1, 2024

Featured Artists Hail From the Florida Panhandle and Cleveland, Ohio “Days Like These,” an exhibition showcasing the latest paintings from...