How California Won By Losing $5 Billion Tesla Battery Plant:

It was supposed to be a $5 billion project, creating 6,500 jobs. That was the hype when Tesla Motors last summer orchestrated a five-state battle to host a huge “gigafactory” where it plans to build batteries for its next generation of electric cars.

Anyone who’s driven one knows the Tesla Model S seems to take off like a bullet from a standing start, pushing driver and passengers back into their seats with strong G-forces.

But the only bullet involved with the luxury electric car company’s battery plant – to be built in association with Japan’s Panasonic Corp. – is the one California dodged by losing the plant to a location near Reno, Nev.

For construction of this plant is not exactly moving like a speeding bullet. Rather, it’s plodding along, at best.

Meanwhile, Nevada has already okayed spending at least $70 million on roads to service the plant, not to mention an unknown amount in property taxes lost to the exemption given the plant as one incentive to build there. Iron workers had erected $15 million worth of steel framing on the site by early winter. Then came an apparent slowdown.

An early March Reno newspaper report quoted a post on the national union job board of the International Brotherhood of Electrical Workers saying “Project Tiger” – the Tesla plant’s code name – “has been cut back by 80 percent at this time. This is all subject to change.” In short, Tesla is hiring far fewer electricians than previously planned.

This could be because of reported problems finding and/or keeping competent project managers on the job — or not.

The development came almost simultaneously with the company downsizing its China production facility, cutting 180 of 600 employees there, or 30 percent of its workforce.

Was there a link? Possibly not, but Tesla wasn’t saying, insisting both that the Nevada plant is right on schedule and that there’s nothing to worry about in China. But if Tesla’s sales of its high-end Model S – which can cost about $120,000 – have slowed, might that affect the pace for rolling out its promised mid-price, mid-size car, due to get its batteries from the Nevada plant?

Company kingpin Elon Musk isn’t saying. The firm sold only 120 cars in China in January, behind its projected pace and one reason Tesla stock has traded lately at more than $40 below its 2014 peak. Musk maintains this was because many urban Chinese don’t have access to garages, where American Tesla owners most frequently recharge their cars.

He insists this is a very temporary glitch, because Tesla is fast building a large chain of recharging stations across much of China, with nearly 700 slots now open in 70 cities.

This all appears to mean great uncertainty for Tesla, and for the state of Nevada, which eventually will pony up $1.3 billion under promises made when it landed the battery plant. No one knows the pace with which the plant will be built. No one knows if it will produce the thousands of expected jobs, for which Nevada will pay well over $100,000 each if all 6,500 materialize – more for each if the plant hires fewer workers.

Nevada has never paid anything like that to casinos or other big employers. Nor has California ever paid so much in corporate welfare. Plus Tesla will pay no local property taxes for years to come and no one knows who will build schools and hire teachers for children of the putative new workers.

That’s what California “lost” when it didn’t get the opportunity to subsidize Tesla’s battery plant, which could have been sited near Stockton. Just now, it looks like this state dodged a significant bullet.

A larger question, of course, is whether any government should make corporate handouts on so grand a scale. Whenever American companies encounter similar government subsidies to their foreign rivals, they gripe about unfair competition.

And yet…Toyota, Nissan, Volkswagen and Mercedes Benz all have gotten similar packages from states like Texas, Tennessee, Alabama and Mississippi.

The ultimate outcome of the Tesla deal is not yet known, but right now it looks like California will be far better off by losing the battery plant than if it had “won” the competition.

in Opinion
Related Posts

Food, Water, and Energy Part 2 of 4

July 21, 2024

July 21, 2024

Last week’s S.M.a,r,t, article (https://smmirror.com/2024/07/sm-a-r-t-column-food-water-and-energy-part-1-of-3/) talked about the seismic risks to the City from getting its three survival essentials, food,...

SM.a.r.t. Column: Food Water and Energy Part 1 of 3

July 14, 2024

July 14, 2024

Civilization, as we know it, requires many things, but the most critical and fundamental is an uninterrupted supply of three...

Letter to the Editor: Criticizing Israeli Policy Is Not Antisemitic

July 10, 2024

July 10, 2024

In the past several months, we’ve seen increasing protests against Israel’s actions in Gaza. We have also seen these protests...

SMA.R.T. WISHES ALL A VERY HAPPY 4TH OF JULY WEEK

July 7, 2024

July 7, 2024

We trust you are enjoying this holiday in celebration of Independence. Independence to be embraced, personally and civically, thru active...

SM.a.r.t Column: Santa Monica Under SCAG’s Boot

June 30, 2024

June 30, 2024

Four years ago, our esteemed colleague Mario Fonda-Bonardi wrote the prescient essay below when much of the legislative development juggernaut...

SM.a.r.t Column: The Up Zoning Scam (Part 2)

June 23, 2024

June 23, 2024

Last week’s SMart article  (https://smmirror.com/2024/06/sm-a-r-t-column-the-up-zoning-scam-part-1/)  discussed the ambitious 8895 units (including 6168 affordable units) that Santa Monica is required to...

SM.a.r.t Column: The Up Zoning Scam (Part 1)

June 16, 2024

June 16, 2024

Over the last few years, the State of California has mandated a massive upzoning of cities to create capacity for...

SM.a.r.t. Column: Shape Up – On Steroids

June 9, 2024

June 9, 2024

Nine years ago, SMa.r.t wrote a series of articles addressing the adaptive re-use of existing structures. We titled one “Shape...

SM.a.r.t Column: The Challenge of Running a City When City Staff Have Different Priorities

June 2, 2024

June 2, 2024

Living in a city has its perks, but it can be a real headache when the folks running the show...

SM.a.r.t. Column: A Path to Affordable Ownership in Santa Monica

May 27, 2024

May 27, 2024

[Note: our guest author today is Andres Drobny, a former Professor of Economics at the University of London, the former...

SM.a.r.t. Column: A Path Forward for Santa Monica: Part II

May 19, 2024

May 19, 2024

As referenced in Part I of this article, the state’s use of faulty statistics and forceful legislation has left a...

SM.a.r.t. Column: A Path Forward for Santa Monica: Part I

May 12, 2024

May 12, 2024

To quickly summarize, California grapples with an ongoing housing crisis spurred by state implementation of over 100 policies and mandates...

SM.a.r.t. Column: Where Will Our Huddled Masses Sleep? Navigating California’s Affordable Housing Mandates

May 5, 2024

May 5, 2024

Just as Lady Liberty beckons the “huddled masses” of immigrants to America, cities like Santa Monica have an ethical obligation...

SM.a.r.t Column: SMCLC SPEAKS

April 28, 2024

April 28, 2024

SMart (Santa Monica Architects for a Responsible Tomorrow) periodically invites guest columnists who have made a significant contribution to the...

SM.a.r.t Column: Building Modern Boxes Lacks Identity

April 21, 2024

April 21, 2024

In the relentless pursuit of modernity, cities worldwide have witnessed the rise of so-called architectural marvels in the form of...