How About Incentives in Bullet Train Contracts?

By Tom Elias

Thomas B. Elias, Columnist

Reports rise almost weekly about missed construction deadlines and other time problems for California’s embattled bullet train project, which hopes to see passengers move between Los Angeles and San Francisco in well under three hours sometime around 2030.

But the state’s High Speed Rail Authority, charged with spending almost $10 billion in state bond money approved by voters nine years ago, along with federal grant money and other funds from state sources like the cap-and-trade program, denies it has missed a single deadline.

“We have not missed any completion dates,” insists project spokeswoman Lisa Marie Alley. The authority even issued a press release announcing it met all federal timing requirements for more than $2.55 billion in 2009 grant money, while generating $4 billion in economic activity in the state.

And yet, no portion of the project, which will eventually also see terminals in Anaheim and Sacramento is anywhere near completion. It’s possible none will be completed if the myriad lawsuits against the project ever succeed.

That’s one reason a report on the Breitbart News California website looked credible at first glance the other day, when it said the authority had extended a deadline for prime contract work by the Tutor-Perini/Zachry/Parsons (TPZP) consortium on the 32-mile first stretch between Madera and south Fresno. Breitbart also said the consortium got an 18 percent raise amounting to almost $8 million for that stretch.

Well… not exactly. The HSR directors actually increased the contingency fund for work on their first segment by $35 million; none earmarked for the TPZP group. The money, said the directors, will “address short-term needs and avoid delaying…critical activities through November.” As of early November, Alley said, the contractors had received none of that money. Nor were any deadlines extended.

So much for the accuracy of “fake news” critic Stephen Bannon, the former top adviser to President Trump who heads Breitbart.

All this, however, begs the question of whether the project can really be on time, as officials claim, when not even one short segment is finished more than two years after construction began.

Which leads to a simple question: Why not put time incentives into bullet train contracts? This is perfectly legal (“We could opt to do that, but… have not done so,” said Alley) and has been effective when the state did use it.

The best examples of incentives speeding work without increasing costs, while boosting local economies far more than the expenses involved, came immediately after the 1989 Loma Prieta earthquake and the 1994 Northridge shock.

After Loma Prieta, incentives were written into a contract with the C.C. Myers construction firm of Rancho Cordova, which rebuilt two bridges on California 1 near Watsonville in 55 days – 45 days less than what was allotted for the job. Myers got an incentive bonus of $30,000 for each day it was early.

It was the same five years later, when two key bridges collapsed along  the world’s busiest road, the I-10 Santa Monica Freeway in Los Angeles. Exactly 66 days later and 74 days ahead of deadline, that freeway reopened and commuters stopped using detours that cost them about 30 minutes in each direction they drove. That ended daily costs to the local economy estimated at well over $1 million per day for delays to goods and services. Myers again did the work, pocketing about $14 million in incentive bonuses, part of which it spent on extra workers and overtime.

The outcome was similar on five other incentive contracts to rebuild earthquake-damaged bridges.

Despite the proven effectiveness of incentives, Caltrans and other state agencies let the practice lapse. The bullet train has no plans to use them, either. “We have and plan to continue to use design-build and or design-bid-build (contracts) that do not include an incentive,” the authority said.

The HSR authority gave no reason for such rigidity, and perhaps it will change its mind and do the logical thing if it ever falls behind a legally-mandated deadline.

But history shows incentives get work done more quickly and create more jobs, even if they are temporary like most construction work. If California’s next governor is smart, he or she will insist on this tactic as a condition of appointment to the authority’s board, whenever vacancies come up.

Related Posts

Food, Water, and Energy Part 2 of 4

July 21, 2024

July 21, 2024

Last week’s S.M.a,r,t, article (https://smmirror.com/2024/07/sm-a-r-t-column-food-water-and-energy-part-1-of-3/) talked about the seismic risks to the City from getting its three survival essentials, food,...

SM.a.r.t. Column: Food Water and Energy Part 1 of 3

July 14, 2024

July 14, 2024

Civilization, as we know it, requires many things, but the most critical and fundamental is an uninterrupted supply of three...

Letter to the Editor: Criticizing Israeli Policy Is Not Antisemitic

July 10, 2024

July 10, 2024

In the past several months, we’ve seen increasing protests against Israel’s actions in Gaza. We have also seen these protests...

SMA.R.T. WISHES ALL A VERY HAPPY 4TH OF JULY WEEK

July 7, 2024

July 7, 2024

We trust you are enjoying this holiday in celebration of Independence. Independence to be embraced, personally and civically, thru active...

SM.a.r.t Column: Santa Monica Under SCAG’s Boot

June 30, 2024

June 30, 2024

Four years ago, our esteemed colleague Mario Fonda-Bonardi wrote the prescient essay below when much of the legislative development juggernaut...

SM.a.r.t Column: The Up Zoning Scam (Part 2)

June 23, 2024

June 23, 2024

Last week’s SMart article  (https://smmirror.com/2024/06/sm-a-r-t-column-the-up-zoning-scam-part-1/)  discussed the ambitious 8895 units (including 6168 affordable units) that Santa Monica is required to...

SM.a.r.t Column: The Up Zoning Scam (Part 1)

June 16, 2024

June 16, 2024

Over the last few years, the State of California has mandated a massive upzoning of cities to create capacity for...

SM.a.r.t. Column: Shape Up – On Steroids

June 9, 2024

June 9, 2024

Nine years ago, SMa.r.t wrote a series of articles addressing the adaptive re-use of existing structures. We titled one “Shape...

SM.a.r.t Column: The Challenge of Running a City When City Staff Have Different Priorities

June 2, 2024

June 2, 2024

Living in a city has its perks, but it can be a real headache when the folks running the show...

SM.a.r.t. Column: A Path to Affordable Ownership in Santa Monica

May 27, 2024

May 27, 2024

[Note: our guest author today is Andres Drobny, a former Professor of Economics at the University of London, the former...

SM.a.r.t. Column: A Path Forward for Santa Monica: Part II

May 19, 2024

May 19, 2024

As referenced in Part I of this article, the state’s use of faulty statistics and forceful legislation has left a...

SM.a.r.t. Column: A Path Forward for Santa Monica: Part I

May 12, 2024

May 12, 2024

To quickly summarize, California grapples with an ongoing housing crisis spurred by state implementation of over 100 policies and mandates...

SM.a.r.t. Column: Where Will Our Huddled Masses Sleep? Navigating California’s Affordable Housing Mandates

May 5, 2024

May 5, 2024

Just as Lady Liberty beckons the “huddled masses” of immigrants to America, cities like Santa Monica have an ethical obligation...

SM.a.r.t Column: SMCLC SPEAKS

April 28, 2024

April 28, 2024

SMart (Santa Monica Architects for a Responsible Tomorrow) periodically invites guest columnists who have made a significant contribution to the...

SM.a.r.t Column: Building Modern Boxes Lacks Identity

April 21, 2024

April 21, 2024

In the relentless pursuit of modernity, cities worldwide have witnessed the rise of so-called architectural marvels in the form of...