The “Big Three” Santa Monica Construction Projects:

The California Incline closed to traffic on Monday, April 20. I made the circuit of the “Big Three,” the three construction projects that have Santa Monicans talking about traffic. Walking from the under construction light rail station at 4th and Colorado, along the under construction Colorado Esplanade, and up Ocean Avenue to the under construction California Incline. All three projects have an estimated end date of Spring 2016.

At mid-morning the Colorado Esplanade was busy with people walking to the Pier and the Park and Downtown and with cars on the westbound only lanes. At the California Incline, PCH and Ocean Ave. were relatively quiet with cars moving normally and people in the park walking and jogging, sitting on the benches, leaning on the fence, and watching the ocean.

The word on the street had Santa Monica in a mad traffic snarl because of the closure of the California Incline. But it seems drivers had gotten the word to find alternate routes. Perhaps enough drivers had found alternate routes to account for the easier than usual Ocean Ave. traffic.

Why three construction projects at once? Why build during the high tourist summer months? Why start the California Incline before the PCH sewer work is complete?

Interim City Manager Elaine Polachek talked about the reasons why the California Incline project was starting now.

“The California Incline Bridge is substandard, meeting only 30 percent of the standards used to evaluate the structural integrity of the bridge. A lot has changed since 1930 when this bridge was built,” Polachek said.

“No matter when we start it will take a year to complete the project even though it’s a fast-track project. We timed it so only one summer season will be affected by construction.”

“We had been told that the PCH sewer construction project would be completed before the California Incline project start date. Unfortunately that didn’t happen. Although we have now been told that it will be completed by June.

“We will be continually responding to daily problems and events and will be tweaking details as things happen to make this as smooth as possible.”

Originally called the “Sunset Trail” the wood fenced path led from Palisades Park to the beach. Wikipedia lists the trail as being built in 1896 and replaced in 1930 and in continuous use until today’s closure.

“Bringing the California Incline to current seismic standards is the reason for this project. We’ve been working on this project for a long time to secure funding and to receive all the approvals necessary to meet the Federal and State standards. Ninety percent of the $20 million cost of the project will be federally funded,” said Susan Cline, Interim Director of Public Works for the City.

“Once the resources and approvals were secured we moved forward as quickly as we could on this project because it is in the interest of public safety.

“The new bridge will be 52 feet wide. There will be two vehicle lanes, two bicycle lanes and a pedestrian walkway. The iconic design of the fence will be maintained.”

The California Incline is on its own schedule, determined by public safety and by guidelines that come with the Federal funding. The two other big construction projects, the light rail station, run by Expo, and the City run Colorado Esplanade are being coordinated so that the Esplanade is ready when the first passengers get off the light rail train at the 4th Street Station.

“The Colorado Esplanade is designed to be an extension of the light rail, a gateway to the downtown, the Pier and Palisades Park,” said Cline.

At a cost of $13 million the Esplanade is funded by a combination of city general funds, federal funds and special revenue funds. The idea behind the Esplanade design was to make it easier and more fun to walk and bike than to drive.

The 6.6 mile light rail line currently under construction will extend Expo from Culver City to Santa Monica. Expo projects that, by 2030, there will be 64,000 people who ride the Expo line along the Downtown Los Angeles/Santa Monica route. The total cost of the line is estimated at $1.5 billion.

For now plan your detours and your alternate routes. But hold on to the thought that 64,000 Expo riders overall will translate into thousands fewer people coming to Santa Monica in cars and easier trips to downtown LA for Santa Monicans. Hold on to knowing that the California Incline will not fall down in an earthquake.

It’s early times, and there are and will be many problems that need to be solved so people can get where they need to go. But in a year maybe there will be a party celebrating the end of construction on the “Big Three” and the reason will be more people walking and biking and people in cars having a much easier time of it.

What Say You?

City project information: www.smconstructs.org

Esplanade Hotline: 626.344.4248

Incline Hotline: 888.303.6026

in Opinion
<>Related Posts

SM.a.r.t. Column: Preserving Santa Monica

December 15, 2024

December 15, 2024

Since Giving Tuesday I’m sure you have been bombarded with appeals from countless organizations, local, national, or even international that...

SM.a.r.t Column: Climbing The Vertical Learning Curve

December 8, 2024

December 8, 2024

The city is facing a financial crisis, the roots of which stretch back decades but have been made worse by...

SM.a.r.t Column: It’s Time To Inspect Balconies

November 24, 2024

November 24, 2024

About nine years ago, a fifth-floor balcony in a Berkeley apartment building collapsed, tragically killing several students gathered on it...

S.M.a.r.t Column: Your City is Broke

November 18, 2024

November 18, 2024

On December 10, the new City council will be seated fresh from their dominant win in the recent elections. There...

SM.a.r.t Column: Moving Ahead to the Future

November 10, 2024

November 10, 2024

As we write this, the election results are still trickling in. We’ll leave the deep analysis to others, but the...

Opinion: Fact Check: Why Vote Yes on Measure QS

November 1, 2024

November 1, 2024

Despite living in a famously progressive region, Santa Monicans are not immune from the same political misinformation and disinformation that...

SM.a.r.t Column: Lack of Oversight and No Accountability

October 31, 2024

October 31, 2024

S.M.a.r.t. periodically invites guest columnists to write opinion articles on topics of particular interests to our readers. Below is an...

SM.a.r.t Column: “Help! I’ve Fallen, and I …!!”, Cries Santa Monica!

October 25, 2024

October 25, 2024

Maybe fallen, but slipping for sure from being a desirable beachfront community that served all equally, the local residents who...

SM.a.r.t. Column: Vote

October 13, 2024

October 13, 2024

In a polarized country or City every vote counts. Regardless of which side of any issue or candidate you support,...

SM.a.r.t Column: Fact-Checking Election-Season Windbaggery

October 6, 2024

October 6, 2024

Claim: The state is requiring Santa Monica to build 9,000 apartments.Answer: Partially true, partially false. Santa Monica has a pretty...

SM.a.r.t. Column: Public Safety and Traffic Enforcement Can Help Save Lives and Revitalize Santa Monica’s Economy

September 29, 2024

September 29, 2024

We wholeheartedly endorse the candidates below for Santa Monica City Council. Their leading campaign platform is for increased safety in...

SM.a.r.t Column: Crime in Santa Monica: A Growing Concern and the Need for Prioritizing Public Safety

September 22, 2024

September 22, 2024

By Michael Jolly Over the past six months, Santa Monica has experienced a concerning rise in crime, sparking heated discussions...

SM.a.r.t Column: Ten New Commandments

September 15, 2024

September 15, 2024

Starting last week,  the elementary school students of Louisiana will all face mandatory postings of the biblical Ten Commandments in...

SM.a.r.t Column: Santa Monica’s Next City Council

September 8, 2024

September 8, 2024

In the next general election, this November 5th, Santa Monica residents will be asked to vote their choices among an...

SM.a.r.t Column: Part II: The Affordability Crisis: Unmasking California’s RHNA Process and Its Role in Gentrification

September 2, 2024

September 2, 2024

Affordability: An Income and Available Asset Gap Issue, Not a Supply Issue (Last week’s article revealed how state mandates became...